Bricklayer SWMS in Tasmania
In Tasmania, bricklayer contractors must prepare a Safe Work Method Statement before starting high risk construction work, under WHS Regulations 2022 (Tas) reg 299, which requires a SWMS before any high risk construction work. The regulator is WorkSafe Tasmania. For bricklayer work the SWMS must be site-specific and cover the high risk categories the trade routinely hits: risk of a person falling more than 2 metres. One SWMS can cover several of those activities. A generic template can be reused for recurring work only if it is reviewed and adapted to each site's hazards first; an unreviewed copy does not meet the requirement.
The SWMS law in Tasmania
Bricklayer work in Tasmania is regulated by WorkSafe Tasmania under the Work Health and Safety Act 2012 (Tas) and the Work Health and Safety Regulations 2022 (Tas). The duty to prepare a SWMS before high risk construction work is set by WHS Regulations 2022 (Tas) reg 299, and the high risk construction work itself is defined in WHS Regulations 2022 (Tas) reg 291. These follow the harmonised model WHS laws, so a SWMS prepared for another harmonised state transfers with a site-specific review.
Tasmania remade its regulations as the WHS Regulations 2022, replacing the 2012 version, so current SWMS duties are cited to the 2022 Regulations and enforced by WorkSafe Tasmania.
Tasmania's industrial manslaughter offence commenced on 2 October 2024, adding serious criminal penalties where a death at work is caused by the conduct of a PCBU or officer. A site-specific SWMS is part of how a bricklayer business shows it identified and controlled the high risk work these duties attach to, rather than relying on a generic template.
High risk work for bricklayer crews
The high risk construction work categories a bricklayer SWMS usually has to cover:
- ✓ Risk of a person falling more than 2 metres
Typical bricklayer activities that each need their own SWMS:
- · Bricklaying above 2 m from scaffolding
- · Brick and block cutting with demolition saws (silica controls)
- · Block wall construction including reinforced cores
- · Brick cleaning with acid solutions
- · Loading scaffolds and materials handling with telehandler
- · Retaining wall construction near excavations
Hazards a bricklayer SWMS has to control
The hazards that recur on bricklayer jobs and that a site-specific SWMS is expected to address:
- ⚠ Falls from scaffolds and trestles
- ⚠ Silica dust from brick cutting
- ⚠ Manual handling of bricks and blocks
- ⚠ Mortar dermatitis and cement burns
- ⚠ Falling objects at perimeter
The rules a bricklayer SWMS is written against
Beyond the general duty in WHS Regulations 2022 (Tas) reg 299, a bricklayer SWMS in Tasmania is written against the specific model WHS duties and standards that apply to the trade's activities:
- § reg 78 and reg 79: manage the risk of ANY fall liable to cause injury when laying from scaffolds and trestles; a fall of more than 2 m is additionally high risk construction work under reg 291
- § AS/NZS 4576: scaffolding guidelines
- § reg 36: hierarchy of controls for silica dust when cutting bricks and blocks
- § reg 44 to reg 47: PPE duties (RPE for dry cutting, gloves for mortar)
What Tasmania builders check before you start
A principal contractor in Tasmania collects your SWMS before your crew goes on site and checks four things: that it is site-specific to this job (not a reused template), that every high risk category for bricklayer work is covered and controlled, that controls follow the hierarchy rather than jumping to PPE, and that it cites Tasmania legislation. SWMS Pack writes to all four: your site details throughout, WHS Regulations 2022 (Tas) reg 299 cited, and an adversarial review pass before delivery.
Common questions
▸Do bricklayer contractors need a SWMS in Tasmania?
Yes, whenever the work involves any high risk construction work, which for bricklayer work it usually does (risk of a person falling more than 2 metres). The duty to prepare it sits with the PCBU carrying out the work, under WHS Regulations 2022 (Tas) reg 299.
▸Which law covers SWMS in Tasmania?
The Work Health and Safety Act 2012 (Tas) and the Work Health and Safety Regulations 2022 (Tas), enforced by WorkSafe Tasmania. These follow the harmonised model WHS laws used in most states.
▸How fast can I get a bricklayer SWMS for a Tasmania site?
About 5 minutes of questions, then the document is generated and verified in a few minutes and downloads straight away, written to Tasmania legislation and to your specific site.
Bricklayer SWMS in other states
New South WalesVictoriaQueenslandWestern AustraliaSouth AustraliaAustralian Capital TerritoryNorthern Territory
Other trades in Tasmania
ElectricianPlumberCarpenterRooferScaffolderConcreterPainterTilerDemolitionExcavation / EarthmovingSolar Installer